ROR retrofit in-progress

Have the roof panels leaning against North wall (so doesn’t kill off rest of the grass). Put the Simpson post base on the anchor bolt after yesterday’s concrete pour for gantry pier and peeled back the exposed sonotube today. Should be ready to cut the 4x4’s for gantry post and install. Still waiting on rest of Aleko inverted track for South side rail (delay with Fedex delivery).